Hawkins served as lead counsel for La Crosse County, Wisconsin in connection with the negotiation of a long-term contract extension to implement a Clean Air Act retrofit of an existing privately owned refuse-derived fuel project serving the region. The contract addressed complex solid waste commitments and processing and ash disposal responsibilities.
Client | County of La Crosse, Wisconsin |
Role | Lead Negotiation Counsel |
Distinction | Major Pollution Control Modifications to Existing Waste-to-Energy Facility |
Delivery Method | Design-Build-Own-Finance-Operate-Maintain (P3) |
Project Size | 73,000 TPY |
Capital Cost | $11 Million |
Contract Value | $35 Million |
Contract Term | 20 Year Extension |
Contract Counterparties | Xcel Energy |